Loveland, Ohio – A sanitary sewer extension project at Butterworth Road and State Route 48 will begin on Tuesday, June 1. There will be a one lane closure with temporary traffic signals provided to maintain traffic.
City Hall says to anticipate traffic delays.
The project consists of installing 1,455′ of 12″ diameter sanitary sewer along SR 48 from approximately Kipp Lane to Butterworth Road and along Butterworth Road. from SR 48 to the future Chimneyridge subdivision tie-in to the south of Brandywine Lane.
The contract final completion date is September 30.