Tag: bridge replacement

  • New, pre-fabricated Loveland Bike Trail bridge will arrive in three sections

    New, pre-fabricated Loveland Bike Trail bridge will arrive in three sections

    Loveland, Ohio – The bridge replacement on the Little Miami Scenic Trail in Historic Downtown Loveland is on track to be completed in May. The new, pre-fabricated bridge will arrive in three sections.

    To accommodate this, the northern portion of Railroad Avenue from Harrison Avenue will be temporarily closed Monday March 4 through Tuesday March 5. The southern portion of Railroad Avenue will remain open to access area businesses. City Hall is encouraging you to park on the other side of town at the Linda Cox Trailside Parking Lot.
  • East Loveland Avenue at Third Street to close January 30 for bridge replacement

    East Loveland Avenue at Third Street to close January 30 for bridge replacement

    Loveland, Ohio – Beginning on January 30, East Loveland Avenue will be closed to through traffic between Third Street and 200 feet east of Fifth Street for approximately six months to replace the bridge over Bares Run Creek. The bridge is near the East Loveland Nature Preserve. A detour route will be in place.

    The contractor for the project, JTM Smith Construction, will post signage for the following detour: East Loveland Avenue – State Route 48 (northbound) – Murdock-Goshen Road – East Loveland Avenue/Dallasburg Road/O-Bannonville Road. Download detour map.

    • “Right Click” to open in a new tab and view larger.

      Clermont County is replacing the bridge. The Metropolitan Sewer District (MSD) will replace and upsize the sanitary sewer from approximately 220 to 362 East Loveland Avenue.

    The city is receiving a state grant of $722,400 in funding to install sidewalks on both sides of the road between 227 to 356 East Loveland Avenue and relocate the water main around the future bridge wingwalls they will also make storm sewer system improvements, and repave a portion of the roadway.

    Project dates are weather-dependent and subject to change.

    If residents have questions about the project, please contact City Manager David Kennedy at (513) 707-1454 or dkennedy@lovelandoh.gov.