Tag: roundabout

  • Columbia Road/Davis Road/Myrtle Avenue intersectionto close for 4 months

    Columbia Road/Davis Road/Myrtle Avenue intersectionto close for 4 months

    Deerfield Township, Ohio – The Columbia Road and Davis Road/Myrtle Avenue intersection will be closed for the construction of a roundabout beginning Monday, July 22, for sixteen weeks.

    The Columbia Road closure location is between addresses 9311 and 9228. All addresses along Davis Road will only have access from the east.

    During Phase 1 of the road closure, Myrtle Avenue will have access from the north until the traffic is switched, then during Phase II – access will be from the south.

    The roundabout will be constructed by Ford Development Corporation and the project is funded by the Warren County Board of County Commissioners, Warren County Engineer’s Office, and Deerfield Township through the Warren County Transportation Improvement District.

    The detour for the Columbia Road closure will utilize Fields-Ertel Road and US22/SR3. The detour for Davis Road closure will utilize Rich Road, Fields-Ertel Road, and US22/SR3. Myrtle Avenue will have access from Columbia Road.

  • King Avenue Bridge improvement will close that portion of the Loveland Bike Trail

    King Avenue Bridge improvement will close that portion of the Loveland Bike Trail

    by David Miller

    Warren County, Ohio – A portion of the Loveland Bike Trail (Little Miami Scenic Bike Trail) is planned to be closed from June 2022 until December 2022, with a two to three-week closure expected in 2023 to tie the new trail into the existing trail.

    A tunnel will be built for a portion of the Little Miami Scenic Bike Trail, which will separate the trail from Grandin Road.

    A new parking lot for trail users will be built and the project also will include a new roundabout at the intersection of the Peters Cartridge Factory development (Cartridge Brewing) and parking lot access for the trail.

    “New wider lanes and shoulders will improve safety for vehicles who use the bridge and separating the bike path from the roadway will significantly improve safety for users of the Little Miami Scenic Bike Trail,” according to a release from Warren County.

    The King Avenue Bridge carries two lanes of traffic across the Little Miami River in Warren County. The bridge will remain in its current two-lane configuration, but the lanes will be widened, and safety shoulders will be added in both directions. The new structure will be built upstream of the existing bridge crossing.

    In addition, a new 10-foot multi-use path will be built on the new bridge that will separate pedestrians from traffic, and a tunnel will be built for a portion of the Little Miami Scenic Bike Trail, which will separate the trail from Grandin Road.

    Traffic will be maintained on the existing roadway for much of 2022, however, King Avenue and Grandin Road near the Little Miami River will each be closed to traffic separately for approximately three to four months in 2023. The closures are necessary so that the new bridge structure can be connected to the existing roadway.

    Access to the development at the Peters Cartridge Factory (Cartridge Brewing) will be limited during different phases of construction.

    Current and Upcoming Construction Activities:

    • Anticipated Construction Duration: March 2022 – December 2023
    • Tree Clearing for Construction Site: March 2022
    • Phase 1 Construction (bridge substructure and roadway fill north of the river): April 2022 – June 2022
    • Various Utility Relocations: April 2022 – July 2022
  • Columbia Road, Davis Road, and Myrtle Ave. Roundabout Project

    Columbia Road, Davis Road, and Myrtle Ave. Roundabout Project

    Deerfield Township, Ohio – The Warren County Engineer’s Office is currently designing a roundabout for the intersection of Columbia Road, Davis Road, and Myrtle Avenue in Deerfield Township. The proposed project may also include a profile adjustment, drainage improvements, large culvert replacement, and a sidewalk along Columbia Road in the project area.  

    The purpose of this project is to improve traffic safety and congestion by constructing a roundabout at this intersection.

    An alternative evaluation report is being completed by Carpenter Marty Transportation to determine the best location and type of roundabout.

    Project Timing: 

    Plans are to be completed by summer 2022. Right of Way acquisition in 2022. Utility relocation in 2023. Construction is tentatively scheduled for 2024.

    Estimated Construction Cost: 

    The project cost estimate is $2,200,000 and the project construction will be funded by the Warren County Engineer and Deerfield Township.

  • Fields-Ertel Road and Columbia Road roundabout opened today

    Fields-Ertel Road and Columbia Road roundabout opened today

    Deerfield/Symmes Township, Ohio – The intersection of Fields-Ertel Road and Columbia/Lebanon Road was re-opened today. The closure was for the construction of a roundabout at the intersection.

    Here… Put this on your phone as you approach! Thank you D Bergheger for the prod!



    RP Diamond Printing & Embroidery

    RP Diamond is the exclusive retailer of LOVELAND HIGH SCHOOL SPIRIT WEAR