A detour will be in place

The Clermont County Engineerā€™s Office provided an update on the improvements taking place in the Branch-Hill Guinea Road area:

  • Ā The water main replacement work will be completed on Tuesday, April 5, weather permitting.
  • The reconstruction and paving of Branch Hill-Guinea Road will begin on Wednesday, April 6. A detour will be required while this work is taking place and will last until Tuesday, May 10, weather permitting. A map is provided below.

This work is part of the Branch Hill-Guinea Road Drainage Improvements Project, which consists of drainage improvements and widening along Branch Hill-Guinea Road between Branch Hill-Loveland and Branch Hill-Miamiville Road.

Phase 1: Work to replace a deteriorated section of water main between Branch Hill-Loveland and Branch Hill-Miamiville Road will begin.

TRAFFIC IMPACTS:Ā Traffic was reduced to one lane with the use of flaggers during work hours.

TIMING:Ā Expected completion: Tuesday, April 5, 2016Ā 

Phase 2: Following the completion of the above water main replacement work, the roadway improvements will begin, including the reconstruction and paving of Branch Hill-Guinea Road.

Improvements will include 12ā€™ travel lanes and 2ā€™ shoulders, as well as curb and gutter work. (The existing lane width is 10ā€™ with little to no shoulder room and deep roadside ditches.)

TRAFFIC IMPACTS:Ā This work will require a full closure of Branch Hill-Guinea Road between Branch Hill-Loveland Road and Branch Hill-Miamiville Road. A detour will be in place that directs traffic from Branch Hill-Guinea Road to Wards Corner Road to I-275 to Loveland-Madeira Road. [See map.]

TIMING:Ā Start date: Wednesday, April 6, 2016

Expected completion: Tuesday, May 10, 2016

Click Map for Larger View

BHG_BHL-to-BHM_Detour_4-6-16-to-5-10-16-(1)

 

fran 10:2015

Your comments can change our community

This site uses Akismet to reduce spam. Learn how your comment data is processed.